Dewes Street
Work Performed:
·
Mobilization of equipment and materials
·
Saw-cutting concrete pavement in locations of
underground utility repairs
·
Met with Village staff on-site to review utility
lay-out
Work Anticipated to be performed, July 16th to
July 20th
·
Begin water main installation along Dewes Street
starting at Spruce Street and working west to Shermer Road.
The heavy construction is starting later than anticipated
due to scheduling conflicts. It is anticipated the water main installation will
begin in the middle of next week. It is planned the contractor will eventually
bring two crews to work on the site at the same time to make up for lost time.
As construction begins, residents will notice it will be
increasingly more difficult to travel along Dewes Street. Delays are
anticipated traveling along the roadway, but we will do everything possible to
minimize the delays to the greatest extent possible.
Thank you in advance for all your patience and
understanding.
Topp Lane
Work Performed:
·
Completed underground utility improvements
including sanitary sewer, storm sewer, and water main installation.
·
Removed existing concrete curb & gutter,
sidewalks, and driveways.
·
Removed existing asphalt pavement and driveways.
·
Installed string-line, graded aggregate, and
performed preparation work for concrete curb & gutter
·
Poured concrete curb & gutter, leaving gaps
in driveways as needed to provide access.
·
Started pouring concrete driveways.
Work Anticipated to be performed, July 16th to
July 20th
·
Complete pouring concrete curb & gutter and
driveways
·
Pour concrete sidewalks
·
Remove excess gravel from roadway
·
Make repairs to existing base materials as
required
·
Grade roadway in preparation for asphalt
pavement.
The roadway reconstruction phase of the project is fully
underway. The concrete curb & gutter and driveways are anticipated to be
completed by the end of the next week. The contractor will also be grading and
getting the roadway ready for new asphalt pavement next week.
If all goes as planned, the first layer of asphalt pavement
will be installed the week of July 23rd. Once this work is
completed, a smooth driving surface will be provided and the amount of dust
will be greatly reduced.
Thanks again for all your patience and understanding throughout
the construction project. Especially those residents that have been without
driveway access during the concrete pouring and curing process.