Dewes Street

Work Performed:

·        sanitary sewer service replacements continuing

·        Started new water main installation from Shermer to Spruce.

 

Work Anticipated to be performed, August 20th to August 24th

·        Continue to replace sanitary sewer services where existing sanitary sewer was replaced

·        Tentatively water main installation should be completed by the end of next week. once completed the main will be filled and start the testing phase.

 

I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.

 

Topp Lane

Work Performed:
No work on Topp Lane. Waiting for the weather to be more conducive for sod installation. Once sod is completed the final lift of Asphalt will be installed.