Dewes Street
Work Performed:
· Sanitary sewer service replacements Completed
· Water Mainline completed
Work Anticipated to be performed, September 4th to September 7th.
· Contractor to fill and test water main.
- Contractor to continue replacing storm sewer
· Contractor to start moving water services to new water main once testing and chlorination complete
I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.
We would like to wish everyone a safe and happy weekend
We would like to wish everyone a safe and happy weekend
Topp Lane
Work Performed:
No work on Topp Lane. Waiting for the weather to be more conducive for sod installation. Once sod is completed the final lift of Asphalt will be installed.