Friday, August 31, 2018

Dewes Street

Work Performed:

·         Sanitary sewer service replacements Completed

·        Water Mainline completed

 

Work Anticipated to be performed, September 4th to September 7th.

·        Contractor to fill and test water main.
  • Contractor to continue replacing storm sewer
·        Contractor to start moving water services to new water main once testing and chlorination complete

I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.
We would like to wish everyone a safe and happy weekend

 

Topp Lane

Work Performed:
No work on Topp Lane. Waiting for the weather to be more conducive for sod installation. Once sod is completed the final lift of Asphalt will be installed.

Friday, August 24, 2018

Dewes Street

Work Performed:

·        sanitary sewer service replacements continuing

·        finish water main, mainline.

 

Work Anticipated to be performed, August 27th to August 31st

·        Continue to replace sanitary sewer services where existing sanitary sewer was replaced.
  • Tentatively begin fire hydrant installation on Dewes
·        Water main fill and begin the testing phase.
  • Possibly start storm sewer work next week

I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.

 

Topp Lane

Work Performed:
No work on Topp Lane. Waiting for the weather to be more conducive for sod installation. Once sod is completed the final lift of Asphalt will be installed.

Friday, August 17, 2018

Dewes Street

Work Performed:

·        sanitary sewer service replacements continuing

·        Started new water main installation from Shermer to Spruce.

 

Work Anticipated to be performed, August 20th to August 24th

·        Continue to replace sanitary sewer services where existing sanitary sewer was replaced

·        Tentatively water main installation should be completed by the end of next week. once completed the main will be filled and start the testing phase.

 

I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.

 

Topp Lane

Work Performed:
No work on Topp Lane. Waiting for the weather to be more conducive for sod installation. Once sod is completed the final lift of Asphalt will be installed.

Friday, August 3, 2018

Water main begins on Dewes St


Dewes Street

Work Performed:

·        sanitary sewer service replacements

·        Started new water main installation from Shermer to Spruce.

 

Work Anticipated to be performed, August 13th to August 17th

·        Continue to replace sanitary sewer services where existing sanitary sewer was replaced

·        Continue water main installation.

 

Thank you once again for your patience and understanding as you drive through and around the construction area.

 

Topp Lane

Work Performed:
 

 

Work Anticipated to be performed, August 13th to August 17th

·        Tentatively adjust Structures in the street
 


The majority of the project is complete.

 

The contractor will not be installing sod until later in the fall when growing conditions are more favorable.

Once the sod is completed the final lift of Asphalt will be installed.