Work Performed:
·
Continued with sanitary sewer replacement at
Spruce Street working west.
Work Anticipated to be performed, July 30th to
August 3rd
·
Complete sanitary sewer main line replacement
from Spruce Street to mid-block per plan
·
Replace sanitary sewer services where existing
sanitary sewer was replaced
·
Begin water main installation.
Thanks for your patience and understanding as you drive
through and around the construction area.
Topp Lane
Work Performed:
·
Paved first layers of asphalt pavement
·
Poured concrete sidewalks
·
Rough grading of landscape behind curb &
gutter
·
Testing of newly installed water main
Work Anticipated to be performed, July 30th to
August 3rd
·
Rough grade landscape
·
Installation of topsoil
·
Pave asphalt driveways.
·
General site clean-up
A majority of the concrete work is now completed. Hopefully
you saw a significant difference in the amount of dust and ease of traveling
along Topp Lane once the first layers of asphalt pavement were completed early
last week.
The contractor will continue to rough grade and clean-up the
disturbed areas behind the curb & gutter and install topsoil next week.
However, sod will not be installed until later in the fall when growing
conditions are more favorable.