Friday, November 2, 2018

Dewes Street

Work Performed this past week:
  •  Started Landscaping on Dewes and should be completed early next week weather permitting
  • Bituminous Driveways will be installed today, Friday

Work Anticipated to be performed, November 5th to November 9th.

·       Landscaping will be completed early next week, weather permitting
  • Bituminous surface will be installed early next week     
 
By the end of next week substantial completion should be achieved for Dewes St. The road will be paved, the landscaping should be completed and only Misc. tasks moving forward.
I would like to Thank each and everyone of the residents for your patience and understanding throughout this project.

Monday, October 29, 2018

Dewes Street

Work Performed this past week:
 

      Contractor finished concrete work.
      Paved Binder on Dewes
 


Work Anticipated to be performed, October 29th to November 2.

·        Landscaping to begin this week


I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.

Thursday, October 11, 2018

Dewes Street

Work Performed this past week:
 

      Contractor finishing road excavation and stone base
 


Work Anticipated to be performed, October 16th to October 19th.

·        Start curb installation on the North side of Dewes on Saturday weather permitting. Will follow up with driveways and sidewalks on the North side Saturday and Monday
       Notices are being passed out to each side to help to help guide you through the phasing of the next few weeks


I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.
 

 
Topp Lane
 Only punch list work remaining for Topp Ln.

Friday, October 5, 2018

Dewes Street

Work Performed this past week:
 

      Contractor finished moving water services from the old main to the new main.
Contractor started the excavation for new aggregate base on Dewes.
 


Work Anticipated to be performed, October 8th to October 12th.

·        Finish road excavation and aggregate base and start curb work, weather permitting
       Notices will be passed out to each home help guide you through the phasing of the next few weeks


I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.
 

 
Topp Lane
 Only punch list work remaining for Topp Ln.
 


Friday, September 21, 2018

Dewes Street

Work Performed:
 

·        Contractor started moving water services from the old main to the new main.

 

Work Anticipated to be performed, September 24th to September 28th.

·        Contractor to continue to move water services all next week


I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.
 

 
Topp Lane
 
Work Performed:
Landscaping has been completed.
Asphalt surface has been completed.

Only punch list work remaining for Topp Ln.

Saturday, September 15, 2018

Dewes Street

Work Performed:
 

·        Water Mainline completed

 

Work Anticipated to be performed, September 10th to September 104th.

·        Contractor to fill and test water main.

·        Contractor to start moving water services to new water main once testing and chlorination complete

I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.
 

 
Topp Lane
 
Work Performed:
Landscaping has been completed.
Asphalt surface course will tentatively be installed.

Only punch list work remaining for Topp Ln.

Sunday, September 9, 2018

Dewes Street

Work Performed:
 

·        Water Mainline completed

 

Work Anticipated to be performed, September 10th to September 104th.

·        Contractor to fill and test water main.

·        Contractor to start moving water services to new water main once testing and chlorination complete

I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.
 

 

Topp Lane

Work Performed:
No work on Topp Lane. Waiting for the weather to be more conducive for sod installation. Once sod is completed the final lift of Asphalt will be installed.