Dewes Street
Work Performed:
· Water Mainline completed
Work Anticipated to be performed, September 10th to September 104th.
· Contractor to fill and test water main.
· Contractor to start moving water services to new water main once testing and chlorination complete
I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.
Work Performed:
Landscaping has been completed.
Asphalt surface course will tentatively be installed.
Only punch list work remaining for Topp Ln.