Sunday, September 9, 2018

Dewes Street

Work Performed:
 

·        Water Mainline completed

 

Work Anticipated to be performed, September 10th to September 104th.

·        Contractor to fill and test water main.

·        Contractor to start moving water services to new water main once testing and chlorination complete

I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.
 

 

Topp Lane

Work Performed:
No work on Topp Lane. Waiting for the weather to be more conducive for sod installation. Once sod is completed the final lift of Asphalt will be installed.