Friday, August 31, 2018

Dewes Street

Work Performed:

·         Sanitary sewer service replacements Completed

·        Water Mainline completed

 

Work Anticipated to be performed, September 4th to September 7th.

·        Contractor to fill and test water main.
  • Contractor to continue replacing storm sewer
·        Contractor to start moving water services to new water main once testing and chlorination complete

I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.
We would like to wish everyone a safe and happy weekend

 

Topp Lane

Work Performed:
No work on Topp Lane. Waiting for the weather to be more conducive for sod installation. Once sod is completed the final lift of Asphalt will be installed.