Topp Lane
Work Performed Previously
·
Installed new 8-inch water main from Waukegan
Road to Hollywood Avenue
·
Replaced sanitary sewer services.
Work Anticipated to be performed next week, May 29th
to June 1st
·
Complete water main installation
·
Begin performing necessary testing for new water
main.
·
Continue with sanitary sewer repairs
·
Begin storm sewer installation
As you are aware, the weather over the past few weeks has
not been favorable with the frequent rain events. Construction has been
delayed, but everything is being done to keep the project on schedule to the
greatest extent possible.
Thanks again for all your patience and understanding.
Dewes Street
Nicor continuing to replace gas main and services along the
project site.