Tuesday, May 29, 2018

Water Main along Topp Lane Installed


Topp Lane
Work Performed Previously
·         Installed new 8-inch water main from Waukegan Road to Hollywood Avenue
·         Replaced sanitary sewer services.

Work Anticipated to be performed next week, May 29th to June 1st  
·         Complete water main installation
·         Begin performing necessary testing for new water main.
·         Continue with sanitary sewer repairs
·         Begin storm sewer installation

As you are aware, the weather over the past few weeks has not been favorable with the frequent rain events. Construction has been delayed, but everything is being done to keep the project on schedule to the greatest extent possible.

Thanks again for all your patience and understanding.

Dewes Street
Nicor continuing to replace gas main and services along the project site.