Tuesday, June 5, 2018

Storm Sewer Installation On-Going


Topp Lane
Work Performed Last Week, May 29th to June 1st
·         Continued with sanitary sewer service replacements
·         Performed sanitary sewer mainline repair
·         Started storm sewer installation.

Work Anticipated to be performed this week, May June 4th to June 7th
·         Perform necessary testing for new water main.
·         Continue with sanitary sewer repairs
·         Continue with storm sewer installation.

Once the water main has been properly tested and the necessary approvals have been received to place the new main into service, water service replacements will begin.  We anticipate water service replacements will begin the week of June 11th.  More information regarding what to expect during this process will be provided.

Thanks again for all your patience and understanding as you deal with the dust, travel delays, and other inconveniences of living within a construction area.