Topp Lane
Work Performed Last Week, June 4th to June 8th
·
Performed necessary testing and received approvals
to place water main into service.
·
Continued
with storm sewer installation.
·
General
site clean-up.
Work Anticipated to be performed this week, June 11th
to June 15th
·
Continue with storm sewer installation.
·
Start water service replacements.
The contractor will begin water service replacements this
week. Water services will be replaced from the new water main to the existing
valve and box located in front of each building. During the water service
replacement, water to individual buildings will be shut-off for approximately
2-3 hours while the transition from the old service to the new service is made.
The contractor will notify each building regarding the approximate time and day
of the water shut-off prior to turning off the water. A notice will be placed
on the front of each building the day prior to the service being replaced.
We appreciate your patience during construction and the
upcoming disruptions in water service.