Friday, June 8, 2018

Water Service Replacements to Begin


Topp Lane
 
Work Performed Last Week, June 4th to June 8th
·         Performed necessary testing and received approvals to place water main into service.
·         Continued with storm sewer installation.
·         General site clean-up.

Work Anticipated to be performed this week, June 11th to June 15th  
·         Continue with storm sewer installation.
·         Start water service replacements.

The contractor will begin water service replacements this week. Water services will be replaced from the new water main to the existing valve and box located in front of each building. During the water service replacement, water to individual buildings will be shut-off for approximately 2-3 hours while the transition from the old service to the new service is made. The contractor will notify each building regarding the approximate time and day of the water shut-off prior to turning off the water. A notice will be placed on the front of each building the day prior to the service being replaced.

We appreciate your patience during construction and the upcoming disruptions in water service.