Dewes Street
Work Performed:
·
sanitary sewer service replacements
·
Started new water main installation from Shermer
to Spruce.
Work Anticipated to be performed, August 13th
to August 17th
·
Continue to replace sanitary sewer services where existing
sanitary sewer was replaced
·
Continue water main installation.
Thank you once again for your patience and understanding as you drive
through and around the construction area.
Topp Lane
Work Performed:
Work Anticipated to be performed, August 13th
to August 17th
·
Tentatively adjust Structures in the street
The majority of the project is complete.
The contractor will not be installing sod until later in the
fall when growing conditions are more favorable.
Once the sod is completed the final lift of Asphalt will be
installed.