Friday, July 27, 2018

Dewes Street: Sanitary Sewer Replacement On-Going. Topp Lane: Landscape Restoration On-Going

Dewes Street
Work Performed:
·         Continued with sanitary sewer replacement at Spruce Street working west.

Work Anticipated to be performed, July 30th to August 3rd
·         Complete sanitary sewer main line replacement from Spruce Street to mid-block per plan
·         Replace sanitary sewer services where existing sanitary sewer was replaced
·         Begin water main installation.

Thanks for your patience and understanding as you drive through and around the construction area.

Topp Lane
Work Performed:
·         Paved first layers of asphalt pavement
·         Poured concrete sidewalks
·         Rough grading of landscape behind curb & gutter
·         Testing of newly installed water main

Work Anticipated to be performed, July 30th to August 3rd  
·         Rough grade landscape
·         Installation of topsoil
·         Pave asphalt driveways.
·         General site clean-up

A majority of the concrete work is now completed.  Hopefully you saw a significant difference in the amount of dust and ease of traveling along Topp Lane once the first layers of asphalt pavement were completed early last week.

The contractor will continue to rough grade and clean-up the disturbed areas behind the curb & gutter and install topsoil next week. However, sod will not be installed until later in the fall when growing conditions are more favorable.