Work Performed:
·
Started sanitary sewer replacement at Spruce
Street working west.
·
Removed existing concrete pavement in areas work
was performed.
Work Anticipated to be performed, July 23rd to
July 27th
·
Continue with sanitary sewer main line
replacement working west from Spruce Street.
Heavy construction has started along Dewes Street. It is
anticipated construction will be on-going through the end of October. There
will be several inconveniences that you will experience during construction
including travel delays and dust. We will be everything possible to minimize
any inconveniences to the greatest extent possible. Thank you in advance
for your patience and understanding.
Topp Lane
Work Performed:
·
Completed installation of concrete driveways and
curb & gutter
·
Excavated roadway
·
Installed new aggregate base course
·
Performed repairs to aggregate base course as
needed.
·
Fine graded existing base course
·
Prepared for asphalt paving
Work Anticipated to be performed, July 23rd to
July 27th
·
Complete concrete sidewalk removal and
replacement
·
Pave first layers of asphalt pavement
·
Rough grade landscape
·
Installation of topsoil
·
Pave asphalt driveways.
Paving the first layers of asphalt pavement is scheduled for
early next week, Monday or Tuesday. Once this work is completed, a smooth
driving surface will be provided and the amount of dust will be greatly
reduced. During the paving day, traveling along Topp Lane will be extremely
difficult due the amount of construction equipment and delivery of
materials. It is anticipated Topp Lane at Waukegan Road will be
impassible; therefore, we would request you utilize Hollywood Avenue when
needed and limit your trips along Topp Lane to the greatest extent possible.
Once the asphalt pavement is installed, the contractor will
work on rough grading and installing topsoil in the disturbed areas of the
parkways. Sod will not be installed under early fall in hopes of more
favorable growing conditions. The installation of topsoil will make the site
appear more organized and completed.
Thanks again for all your patience as the major construction
work is nearing an end.