Friday, August 24, 2018

Dewes Street

Work Performed:

·        sanitary sewer service replacements continuing

·        finish water main, mainline.

 

Work Anticipated to be performed, August 27th to August 31st

·        Continue to replace sanitary sewer services where existing sanitary sewer was replaced.
  • Tentatively begin fire hydrant installation on Dewes
·        Water main fill and begin the testing phase.
  • Possibly start storm sewer work next week

I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.

 

Topp Lane

Work Performed:
No work on Topp Lane. Waiting for the weather to be more conducive for sod installation. Once sod is completed the final lift of Asphalt will be installed.