Dewes Street
Work Performed:
· sanitary sewer service replacements continuing
· finish water main, mainline.
Work Anticipated to be performed, August 27th to August 31st
· Continue to replace sanitary sewer services where existing sanitary sewer was replaced.
- Tentatively begin fire hydrant installation on Dewes
· Water main fill and begin the testing phase.
- Possibly start storm sewer work next week
I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.
Topp Lane
Work Performed:
No work on Topp Lane. Waiting for the weather to be more conducive for sod installation. Once sod is completed the final lift of Asphalt will be installed.