Dewes Street

Work Performed:
 

·        Contractor started moving water services from the old main to the new main.

 

Work Anticipated to be performed, September 24th to September 28th.

·        Contractor to continue to move water services all next week


I would like to Thank You once again for your patience and understanding as you drive through and around the construction area.
 

 
Topp Lane
 
Work Performed:
Landscaping has been completed.
Asphalt surface has been completed.

Only punch list work remaining for Topp Ln.