Sunday, July 15, 2018

Dewes Streeet: Underground Utility Work to Begin. Topp Lane: Road Reconstruction Continues

Dewes Street
Work Performed:
·         Mobilization of equipment and materials
·         Saw-cutting concrete pavement in locations of underground utility repairs
·         Met with Village staff on-site to review utility lay-out

Work Anticipated to be performed, July 16th to July 20th
·         Begin water main installation along Dewes Street starting at Spruce Street and working west to Shermer Road.

The heavy construction is starting later than anticipated due to scheduling conflicts. It is anticipated the water main installation will begin in the middle of next week.  It is planned the contractor will eventually bring two crews to work on the site at the same time to make up for lost time.

As construction begins, residents will notice it will be increasingly more difficult to travel along Dewes Street. Delays are anticipated traveling along the roadway, but we will do everything possible to minimize the delays to the greatest extent possible.

Thank you in advance for all your patience and understanding.

Topp Lane
Work Performed:
·         Completed underground utility improvements including sanitary sewer, storm sewer, and water main installation.
·         Removed existing concrete curb & gutter, sidewalks, and driveways.
·         Removed existing asphalt pavement and driveways.
·         Installed string-line, graded aggregate, and performed preparation work for concrete curb & gutter
·         Poured concrete curb & gutter, leaving gaps in driveways as needed to provide access.
·         Started pouring concrete driveways.

Work Anticipated to be performed, July 16th to July 20th
·         Complete pouring concrete curb & gutter and driveways
·         Pour concrete sidewalks
·         Remove excess gravel from roadway
·         Make repairs to existing base materials as required
·         Grade roadway in preparation for asphalt pavement.

The roadway reconstruction phase of the project is fully underway. The concrete curb & gutter and driveways are anticipated to be completed by the end of the next week. The contractor will also be grading and getting the roadway ready for new asphalt pavement next week.

If all goes as planned, the first layer of asphalt pavement will be installed the week of July 23rd.  Once this work is completed, a smooth driving surface will be provided and the amount of dust will be greatly reduced.

Thanks again for all your patience and understanding throughout the construction project. Especially those residents that have been without driveway access during the concrete pouring and curing process.

Friday, June 29, 2018

Topp Lane: Roadway Reconstruction to Begin. Dewes Street: Underground Utility Improvements begin Week of July 9th


Dewes Street
Underground utility work is expected to begin the week of July 9th.  Next week, the contractor will begin mobilizing equipment, delivering materials, saw cutting the pavement, and other minor work items in preparation to start heavy construction.

Topp Lane
Work Performed Last Week, June 25th to June 29th  
·         Completed water service replacements
·         Completed abandonment of existing water main along Topp Lane
·         Completed sanitary sewer repairs.
·         Continued to work on storm sewer improvements
 
Work Anticipated to be performed this week, July 2nd to July 6th  
·         Complete storm sewer improvements
·         Miscellaneous tasks such as adjusting structures and installing manhole frames
·         Site Clean-up prior to July 4th Holiday
·         Thursday following July 4th Holiday, begin roadway reconstruction.

The underground utility portion of the project will be completed by the July 4th Holiday.  The contractor will spend some time early next week performing general site clean-up and miscellaneous tasks to prepare the site for roadway reconstruction. 

Next Thursday, the contractor is anticipating to begin the roadway reconstruction phase of the project. This work will include removing the remaining asphalt pavement, excavating the existing base materials as needed to acquire a stable roadway base, installation of new aggregate base materials, new concrete curb & gutter on both sides of the roadway, and new asphalt pavement.  The length of time this work will take will be based on how much existing material needs to be removed to get to a stable base.

During roadway reconstruction, the entire width of the roadway will be excavated during the day. It will be difficult to travel along Topp Lane.  Driveway and roadway access will be restricted during working hours, but restored at the end of each day. Additional information will be provided next week.

Thanks again for all your understanding as the project moves into the next phase of construction and the various inconveniences that you will experience.

Have a safe and enjoyable July 4th Holiday.

Monday, June 18, 2018

Dewes Street - Resident Preconstruction Meeting, June 18th at 6:00 PM. Topp Lane - Water Service Replacement Begin

Topp Lane and Dewes Street Improvements 

Dewes Street
Resident  Preconstruction Meeting scheduled for Monday, June 18th from 6:00 PM to 6:45 PM at the Village Hall, 2500 East Lake Avenue, Glenview, IL.  Hope to see you there and learn about the upcoming project.

 
Topp Lane
Work Performed Last Week, June 11th to June 15th
·         Continued with storm sewer installation
·         Continued with sanitary sewer repairs
·         Received necessary approvals in order for water service replacements to begin.
·         General site clean-up.

Work Anticipated to be performed this week, June 18th to June 22nd
·         Water service replacements.
·         Continue with storm sewer installation.
·         Sanitary Sewer repairs.

The contractor will begin water service replacements this week. Water services will be replaced from the new water main to the existing valve and box located in front of each building. During the water service replacement, water to individual buildings will be shut-off for approximately 2-3 hours while the transition from the old service to the new service is made. The contractor will notify each building regarding the approximate time and day of the water shut-off prior to turning off the water. A notice will be placed on the front of each building the day prior to the service being replaced. It is anticipated the water service replacements will take 1-2 weeks to completed.

We appreciate your patience during construction. Over the past several weeks, a significant amount of debris has accumulated along the roadway. We worked with the contractor to ensure the area was cleaned-up and made more orderly.

Friday, June 8, 2018

Water Service Replacements to Begin


Topp Lane
 
Work Performed Last Week, June 4th to June 8th
·         Performed necessary testing and received approvals to place water main into service.
·         Continued with storm sewer installation.
·         General site clean-up.

Work Anticipated to be performed this week, June 11th to June 15th  
·         Continue with storm sewer installation.
·         Start water service replacements.

The contractor will begin water service replacements this week. Water services will be replaced from the new water main to the existing valve and box located in front of each building. During the water service replacement, water to individual buildings will be shut-off for approximately 2-3 hours while the transition from the old service to the new service is made. The contractor will notify each building regarding the approximate time and day of the water shut-off prior to turning off the water. A notice will be placed on the front of each building the day prior to the service being replaced.

We appreciate your patience during construction and the upcoming disruptions in water service.

Tuesday, June 5, 2018

Storm Sewer Installation On-Going


Topp Lane
Work Performed Last Week, May 29th to June 1st
·         Continued with sanitary sewer service replacements
·         Performed sanitary sewer mainline repair
·         Started storm sewer installation.

Work Anticipated to be performed this week, May June 4th to June 7th
·         Perform necessary testing for new water main.
·         Continue with sanitary sewer repairs
·         Continue with storm sewer installation.

Once the water main has been properly tested and the necessary approvals have been received to place the new main into service, water service replacements will begin.  We anticipate water service replacements will begin the week of June 11th.  More information regarding what to expect during this process will be provided.

Thanks again for all your patience and understanding as you deal with the dust, travel delays, and other inconveniences of living within a construction area.

Tuesday, May 29, 2018

Water Main along Topp Lane Installed


Topp Lane
Work Performed Previously
·         Installed new 8-inch water main from Waukegan Road to Hollywood Avenue
·         Replaced sanitary sewer services.

Work Anticipated to be performed next week, May 29th to June 1st  
·         Complete water main installation
·         Begin performing necessary testing for new water main.
·         Continue with sanitary sewer repairs
·         Begin storm sewer installation

As you are aware, the weather over the past few weeks has not been favorable with the frequent rain events. Construction has been delayed, but everything is being done to keep the project on schedule to the greatest extent possible.

Thanks again for all your patience and understanding.

Dewes Street
Nicor continuing to replace gas main and services along the project site.

Friday, May 11, 2018

Water Main Started on Topp Lane

Topp Lane

Work Performed This Week, May 7th to May 11th
·         Sanitary sewer service replacements
·         Connected to existing water main at Waukegan Road 

Work Anticipated to be performed next week, May 14th to May 18th
·         Continue with water main installation starting near Waukegan Road east to Hollywood Avenue
·         Continue with sanitary sewer service replacements

As construction has started, there is an increase of construction traffic along the roadway. Please use caution as you driving along the site and backing out of your driveway.  It is anticipated that some settlement will occur over the gravel trenches that were previously excavated.  Please be assured everything will be done to keep those areas as smooth as possible, but please drive slowly. 

 There have been some delays in construction due to the recent rain events, but work is progressing as expected.

Thanks again for all your patience during the construction operations.

Dewes Street

Nicor is currently in the process of replacing the existing gas main and services along Dewes Street. Once that work is completed, the Dewes Street Roadway and Utility Improvement project will begin.  More information regarding the start date will be provide as the schedules are finalized.